Website Development Process

timeline_pre_loader
Turnaround for a basic website development project is typically 6-8 weeks from start to finish
1-2 Business Days

Follow-Up Call or Meeting

Design Process Begins

5-7 Business Days
3-5 Business Days

Client Provides Feedback On Round 1

Designer Reaches Out With Any Questions

3-5 Business Days
3-5 Business Days

Client Approves Design Comp

Content For All Interior Pages Due*

*We don’t just drop text into a template. We custom-build each page around your unique content. Therefore, we cannot proceed further in the development process until we receive the remainder of your content.
3-5 Business Days

Developer Builds Out Website Based on Design Comp

7-10 Business Days
3-5 Business Days

Client Provides Any Revisions Needed to Staging Site

3-5 Business Days

Final Approval of Desktop Version From Client

1-2 Business Days

Developer Addresses Design on Mobile Devices

3-5 Business Days